May 21, 2025

Update: Sherford Phase 3AB Earthworks

Our team are hard at work on the earthworks for Phase 3AB at Sherford. Overall, for this phase of work we're expecting over 200,000m³ of Cut and over 325,000m³ of Fill — and we're currently around 50% through the cut and 35% through the fill. A huge operation that continues to advance at pace.